Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 203: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Project Number:
Title:
Umatilla Fish Passage Operations
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
73982 REL 203
Contract Title:
1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Continuation:
Previous: Next:
73982 REL 177: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Status:
Issued
Contract Description:
In 2011, the Umatilla Fish Passage Operations project and Walla Walla Fish Passage Operations project were combined into one project to relieve administrative and contracting workloads. These projects were historically one project and were split at the request of BPA prior to being able to track activities in separate basins. With the Pisces management tool, work activities can be tracked by basin, therefore the need for the projects to be separated in no longer accurate. For interim history of the Walla Walla work activities (2000 - 2010) please refer to project 2000-033-00.

Umatilla Basin Background
In the 1980's, CTUIR and ODFW began implementing the Umatilla Fisheries Restoration Plan. An integral part of that effort was to address inadequate flow and migration conditions by constructing fish passage facilities, initiating a trap and haul program, and implementing the Umatilla Basin Project flow enhancement effort.

Project Goal: The long-term goal of the project is to increase the survival of both adult and juvenile migrants in the Umatilla Basin. Our approach is focused on three areas: 1) Monitoring, coordination and operation of trapping and passage facilities and river conditions; 2) Coordination and implementation of flow enhancement efforts; and 3) Provide transportation equipment to safely haul both adult and juvenile migrants when inadequate passage conditions exist.  

Walla Walla Basin Background
In the late 1990's, CTUIR, ODFW and WDFW, along with many other agencies, began implementing fisheries restoration efforts in the Walla Walla Basin. An integral part of these efforts is to alleviate the inadequate fish passage conditions in the basin. Migration conditions are being addressed by removing diversion structures, constructing and/or modifying new and existing fish passage facilities, implementing minimum flow requirements, and providing trap and haul efforts when needed.

Project Goal:  The long-term goal of the project is to increase adult returns of spring Chinook, summer steelhead, and bull trout to the Walla Walla River annually by increasing survival of both adult and juvenile migrants. Our approach is focused on three areas: 1) Monitoring of flow and passage conditions; 2) Operation of trapping and fish passage facilities and transportation equipment; 3) Coordination of trapping and fish passage facilities, transportation, and flow enhancement efforts.    
Account Type(s):
Expense
Contract Start Date:
01/01/2024
Contract End Date:
12/31/2024
Current Contract Value:
$840,088
Expenditures:
$182,288

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Project Management 12/31/2024
Effective Environmental Compliance and Documentation B: 165. Environmental Compliance 12/31/2024
Effective Coordination and Participation of Umatilla Passage Program C: 191. Coordinate Passage Facility Operations-Umatilla Basin 12/31/2024
Coordinate passage facility operations D: 191. Coordinate Passage Facility Operations-Walla Walla Basin 12/31/2024
Effective Flow Management Strategy E: 191. Coordinate Umatilla Passage Program-McKay Release 12/31/2024
Provide review and comment throughout project year. F: 122. Provide Facility Design Technical Review-Walla Walla Basin 12/31/2024
Provide technical support for fish passage improvement efforts. G: 122. Provide Facility Design Technical Review-Umatilla Basin 12/31/2024
Effective Maintenance Program H: 61. Maintain and Operate Hauling Equipment-Umatilla and Walla Walla Basin 12/31/2024
Transportation Assistance. I: 66. Provide Transportation Assistance-Umatilla Basin 12/31/2024
Collection of Umatilla Broodstock J: 66. Provide broodstock for artificial production program-Umatilla Basin 12/31/2024
Safe transport of adult juvenile salmonids K: 28. Transport of Upstream And Downstream Migrants-Umatilla Basin 07/31/2024
Safe transport of fish collected during salvage operations L: 28. Coordinate and complete salvage operations-Walla Walla Basin 12/31/2024
V-trap Report M: 28. Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin 08/31/2024
Produce accessible, error-checked datasets N: 157. Adult Return and Transport Data-Umatilla Basin 12/31/2024
Final AOP O: 174. Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin 09/30/2024
Final AOP Completed P: 174. Provide Input/Information as needed for Umatilla Hatchery AOP 09/30/2024
Project Monthly Status Reports Q: 141. Other Reports for BPA 12/31/2024
Completed Annual Report R: 132. Umatilla Basin: CTUIR Annual Report (10-1-23 - 9-30-24) 12/31/2024
Completed Annual Report S: 132. Walla Walla Basin: CTUIR Annual Report (10-1-23 - 9-30-24) 12/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project Management
B 165 Environmental Compliance
C 191 Coordinate Passage Facility Operations-Umatilla Basin
D 191 Coordinate Passage Facility Operations-Walla Walla Basin
E 191 Coordinate Umatilla Passage Program-McKay Release
F 122 Provide Facility Design Technical Review-Walla Walla Basin
G 122 Provide Facility Design Technical Review-Umatilla Basin
H 61 Maintain and Operate Hauling Equipment-Umatilla and Walla Walla Basin
I 66 Provide Transportation Assistance-Umatilla Basin
J 66 Provide broodstock for artificial production program-Umatilla Basin
K 28 Transport of Upstream And Downstream Migrants-Umatilla Basin
L 28 Coordinate and complete salvage operations-Walla Walla Basin
M 28 Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin
N 157 Adult Return and Transport Data-Umatilla Basin
O 174 Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin
P 174 Provide Input/Information as needed for Umatilla Hatchery AOP
Q 141 Other Reports for BPA
R 132 Umatilla Basin: CTUIR Annual Report (10-1-23 - 9-30-24)
S 132 Walla Walla Basin: CTUIR Annual Report (10-1-23 - 9-30-24)
T 185 Periodic Status Reports for BPA